项目进度计划
来源:动视网
责编:小OO
时间:2025-09-24 17:08:01
项目进度计划
6#施工进度计划时间施工项目8-208-238-268-299-19-49-79-109-139-169-19-9-229-259-2810-110-410-710-1010-1310-1610-1910-2210-25Q10-Q23桩管沟测量放线Q10-Q23桩管沟扫线Q10-Q23桩管道布管Q10-Q23桩管道焊接Q10-Q23桩管沟开挖Q10-Q23桩管道探伤及补口补伤Q10-Q23桩管道下沟及连头Q10-Q23桩管沟回填Q3-Q9桩测量放线Q3-Q9桩管沟扫线Q3-Q9桩管道布管Q3-
导读6#施工进度计划时间施工项目8-208-238-268-299-19-49-79-109-139-169-19-9-229-259-2810-110-410-710-1010-1310-1610-1910-2210-25Q10-Q23桩管沟测量放线Q10-Q23桩管沟扫线Q10-Q23桩管道布管Q10-Q23桩管道焊接Q10-Q23桩管沟开挖Q10-Q23桩管道探伤及补口补伤Q10-Q23桩管道下沟及连头Q10-Q23桩管沟回填Q3-Q9桩测量放线Q3-Q9桩管沟扫线Q3-Q9桩管道布管Q3-
6# 施工进度计划
时间
施工项目 | 8-20 | 8-23 | 8-26 | 8-29 | 9-1 | 9-4 | 9-7 | 9-10 | 9-13 | 9-16 | 9-19 | -9-22 | 9-25 | 9-28 | 10-1 | 10-4 | 10-7 | 10-10 | 10-13 | 10-16 | 10-19 | 10-22 | 10-25 |
Q10-Q23桩管沟测量放线 | | | | | | | | | | | | | | | | | | | | | | | |
Q10-Q23桩管沟扫线 | | | | | | | | | | | | | | | | | | | | | | | |
Q10-Q23桩管道布管 | | | | | | | | | | | | | | | | | | | | | | | |
Q10-Q23桩管道焊接 | | | | | | | | | | | | | | | | | | | | | | | |
Q10-Q23桩管沟开挖 | | | | | | | | | | | | | | | | | | | | | | | |
Q10-Q23桩管道探伤及补口补伤 | | | | | | | | | | | | | | | | | | | | | | | |
Q10-Q23桩管道下沟及连头 | | | | | | | | | | | | | | | | | | | | | | | |
Q10-Q23桩管沟回填 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩测量放线 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩管沟扫线 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩管道布管 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩管道焊接 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩管沟开挖 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩管道探伤及补口补伤 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩管道下沟及连头 | | | | | | | | | | | | | | | | | | | | | | | |
Q3-Q9桩管沟回填 | | | | | | | | | | | | | | | | | | | | | | | |
Q1-Q3桩测量放线及扫线 | | | | | | | | | | | | | | | | | | | | | | | |
Q1-Q3桩管道布管 | | | | | | | | | | | | | | | | | | | | | | | |
Q1-Q3桩管道焊接 | | | | | | | | | | | | | | | | | | | | | | | |
时间 施工项目 | 8-20 | 8-23 | 8-26 | 8-29 | 9-1 | 9-4 | 9-7 | 9-10 | 9-13 | 9-16 | 9-19 | -9-22 | 9-25 | 9-28 | 10-1 | 10-4 | 10-7 | 10-10 | 10-13 | 10-16 | 10-19 | 10-22 | 10-25 |
Q1-Q3桩管沟开挖 | | | | | | | | | | | | | | | | | | | | | | | |
Q1-Q3桩管道探伤及补口补伤 | | | | | | | | | | | | | | | | | | | | | | | |
Q1-Q3桩管道下沟及连头 | | | | | | | | | | | | | | | | | | | | | | | |
Q1-Q3桩管沟回填 | | | | | | | | | | | | | | | | | | | | | | | |
Q9-Q10包茂高速穿越 | | | | | | | | | | | | | | | | | | | | | | | |
管道整体试压吹到 | | | | | | | | | | | | | | | | | | | | | | | |
编制单位:中石化工建设有限公司靖边工业园区项目部