工期安排横道图
来源:动视网
责编:小OO
时间:2025-09-23 10:51:31
工期安排横道图
附表一:工期安排计划表1海口电厂6#、7#机组设备拆除施工计划总安排工期主要工序2017.5.10-5.316.1-6.307.1-7.318.1-8.3111.1-11.3012.1-12.312018.1.1-1.312.1-2.20方案预审设备拆除变压器电缆电器汽轮附件汽轮主体脱硫除尘锅炉附件锅炉主体爆破备案厂房拆除主厂房、煤仓间锅炉房爆破锅炉房清渣、切割钢筋烟囱爆破烟囱清渣、切割钢筋收尾验收表2海口电厂6#、7#机组配套180m烟囱及两座50.4m锅炉厂房拆除爆破工期安排计划工期(天)
导读附表一:工期安排计划表1海口电厂6#、7#机组设备拆除施工计划总安排工期主要工序2017.5.10-5.316.1-6.307.1-7.318.1-8.3111.1-11.3012.1-12.312018.1.1-1.312.1-2.20方案预审设备拆除变压器电缆电器汽轮附件汽轮主体脱硫除尘锅炉附件锅炉主体爆破备案厂房拆除主厂房、煤仓间锅炉房爆破锅炉房清渣、切割钢筋烟囱爆破烟囱清渣、切割钢筋收尾验收表2海口电厂6#、7#机组配套180m烟囱及两座50.4m锅炉厂房拆除爆破工期安排计划工期(天)
附表一:工期安排计划
表1 海口电厂6#、7#机组设备拆除施工计划总安排
工 期
主要工序 | 2017.5.10-5.31 | 6.1-6.30 | 7.1-7.31 | 8.1-8.31 | 11.1-11.30 | 12.1-12.31 | 2018.1.1-1.31 | 2.1-2.20 |
| 方案预审 | | | | | | | | | | | | | | | | | | | | | | |
设 备 拆除 | 变压器 | | | | | | | | | | | | | | | | | | | | | | |
电缆电器 | | | | | | | | | | | | | | | | | | | | | | |
汽轮附件 | | | | | | | | | | | | | | | | | | | | | | |
汽轮主体 | | | | | | | | | | | | | | | | | | | | | | |
脱硫 | | | | | | | | | | | | | | | | | | | | | | |
除尘 | | | | | | | | | | | | | | | | | | | | | | |
锅炉附件 | | | | | | | | | | | | | | | | | | | | | | |
锅炉主体 | | | | | | | | | | | | | | | | | | | | | | |
| 爆破备案 | | | | | | | | | | | | | | | | | | | | | | |
厂房拆除 | 主厂房、煤仓间 | | | | | | | | | | | | | | | | | | | | | | |
锅炉房爆破 | | | | | | | | | | | | | | | | | | | | | | |
锅炉房清渣、切割钢筋 | | | | | | | | | | | | | | | | | | | | | | |
烟囱爆破 | | | | | | | | | | | | | | | | | | | | | | |
烟囱清渣、切割钢筋 | | | | | | | | | | | | | | | | | | | | | | |
| 收尾 | | | | | | | | | | | | | | | | | | | | | | |
| 验收 | | | | | | | | | | | | | | | | | | | | | | |
表2 海口电厂6#、7#机组配套180m烟囱及两座50.4m锅炉厂房拆除爆破工期安排计划
工 期(天)
主要工序 | 2 | 4 | 6 | 8 | 10 | 12 | 14 | 16 | 18 | 20 | 22 | 24 | 26 | 28 | 30 | 32 | 34 | 36 | 38 | 40 | 42 | 44 | 46 | 48 | 50 | 52 |
对应日期 | 2017.11.10-11.19 | 2017.11.20-11.29 | 2017.11.30-12.9 | 2017.12.10-12.19 | 2017.12.20-12.31 |
施工准备 | | | | | | | | | | | | | | | | | | | | | | | | | | |
6#、7#锅炉房 钻孔 | | | | | | | | | | | | | | | | | | | | | | | | | | |
试爆 | | | | | | | | | | | | | | | | | | | | | | | | | | |
装药、防护 | | | | | | | | | | | | | | | | | | | | | | | | | | |
搭设缓冲带 | | | | | | | | | | | | | | | | | | | | | | | | | | |
爆破 | | | | | | | | | | | | | | | | | | | | | | | | | | |
爆堆处理、清运 | | | | | | | | | | | | | | | | | | | | | | | | | | |
烟囱钻孔 | | | | | | | | | | | | | | | | | | | | | | | | | | |
试爆 | | | | | | | | | | | | | | | | | | | | | | | | | | |
定向窗、减荷槽 预处理 | | | | | | | | | | | | | | | | | | | | | | | | | | |
装药、防护 | | | | | | | | | | | | | | | | | | | | | | | | | | |
减震沟、缓冲土墙搭设 | | | | | | | | | | | | | | | | | | | | | | | | | | |
烟囱爆破 | | | | | | | | | | | | | | | | | | | | | | | | | | |
爆堆处理、清运 | | | | | | | | | | | | | | | | | | | | | | | | | | |
竣工验收 | | | | | | | | | | | | | | | | | | | | | | | | | | |
注:具备进场日期为2017年11月10日,即以次日为拆除爆破工程施工工期计划的起始日期,拆除爆破施工进场前已完成机组设备的拆除工作。
工期安排横道图
附表一:工期安排计划表1海口电厂6#、7#机组设备拆除施工计划总安排工期主要工序2017.5.10-5.316.1-6.307.1-7.318.1-8.3111.1-11.3012.1-12.312018.1.1-1.312.1-2.20方案预审设备拆除变压器电缆电器汽轮附件汽轮主体脱硫除尘锅炉附件锅炉主体爆破备案厂房拆除主厂房、煤仓间锅炉房爆破锅炉房清渣、切割钢筋烟囱爆破烟囱清渣、切割钢筋收尾验收表2海口电厂6#、7#机组配套180m烟囱及两座50.4m锅炉厂房拆除爆破工期安排计划工期(天)